MASVINGO – Bulawayo mayor, David Coltart has made startling claims that construction companies linked to politicians have been taking shortcuts in the construction of the 84% complete Harare-Beitbridge Highway thereby severely compromising the quality and durability of the 582km road.
Coltart called for an independent audit to ascertain his claims.
However, in a response to questions by Masvingo Mirror, Deputy Director of Roads Construction in the Ministry of Roads and Infrastructural Development, Engineer Virginia Mawere said the allegations by Coltart were technically not possible, otherwise the roads would not have passed the tests.
She said that the Ministry was going to commission an independent technical assessment of selected highways and invited parties with technical evidence of non-compliance to submit it formally to the Permanent Secretary’s office.
Coltart made the allegations during a plenary discussion at GIBS International Business School, Pretoria University in South Africa with reference to corruption in Zimbabwe and the US$20 million in cash splashed by various businessman and politicians at the wedding of billionaire Kudakwashe Tagwirei’s son, Taonanyasha John Tagwirei in Harare on May 24 2026.
During the panel interview in which one of the panelists was lawyer Tendai Biti, Coltart said State capture in Zimbabwe is on steroids and corruption in the country will make the Guptas look like a bunch of choir boys.
Turning to Harare – Beitbridge Highway whose construction started in 2019, Coltart said he has it on good authority that road construction companies are supposed to use granite chips in building the roads but four of the five companies have been mixing sand with the granite chips.
Companies contracted on the highway are Bitumen World, Masimba Holdings, Tensor Systems, Exodus and Company and Fossil Contracting. Ordinary members of the public have been commenting on the vast difference in quality of work on the various road sections including road signs, road lines, bumpiness etc.
“If you drive on those parts of the road, it looks good but they are starting to deteriorate. The part of the road constructed by the company which used granite chips correctly is good,” said Coltart.
He said that the parts of the roads constructed by these four companies which are close to politicians are already showing signs of deterioration although the road is about three years old.
Masimba Holdings Marketing Executive, Itai Magande dismissed the allegations. He said the company was not going to respond to claims that are not supported by evidence.
“It is Coltart’s view and there is no evidence to support the allegations on the ground,” said Magande.
Recently one of the companies had to redo a section of a road linking to a new bridge in Masvingo after it was condemned.
Tensor Systems co-director, Engineer Ngonidzashe Musowe referred questions to the Ministry of Transport and Infrastructural Development. He said that the ministry was responsible for inspecting and certifying work carried out by contractors on major government road projects.
“The Ministry of Transport inspects all works done by contractors on major government roads. As contractors we are not allowed to comment to the media,” said Musowe.
Efforts to get comments from Bitumen, Exodus and Fossil were fruitless.
“I do believe that there needs to be independent audits of nearly all government tenders including the construction of the Beitbridge Border Post, the Beitbridge-Harare road, the Trabablas Interchange and ZEC 2023 election procurement exercise, amongst others,” he said.
“The allegation is technically implausible. Granite chips and sand perform entirely different structural roles in bituminous pavement and are not interchangeable. Any such substitution would have produced immediately detectable failures in Marshall Stability testing, mix design approval, and bitumen extraction tests – all of which were contractually mandated at production and post lay stages. The substitution alleged could not have passed this testing regime undetected” said Mawere.
“The ministry does not accept characterisations made without reference to specific test certificates, contract sections, or verifiable site data. Any party holding such evidence is invited to submit it formally to the Permanent Secretary” she said.
New Harare-Beitbridge Highway will not last – Coltart