SEKE– Manyame Rural District Council, one of the 10 local authorities of Mash East managed to maintain all its roads in 2025 and even do others for the second time, District Engineer Christopher George has said.
The local authority had a road maintenance target of 532km and it exceeded this and maintained a total chain age of 561km.
“Our road network covers 532 km, which was our set target but we managed to maintain 561 km. This means we revisited and worked on some roads more than once within the district,” said Engineer George.
The local authority’s road maintenance target this year is 551 km. So far in the first quarter, Manyame RDC has covered 180.3 km partnering with Rural Infrastructure Developement Agency (RIDA) and Ministry of Transport (MoT) and there are plans to increase the target by undertaking new road construction projects.
The council’s ERRP budget allocation from ZINARA for this year is approximately zwl$3,366 844,08. Of this, 80% is allocated to periodic maintenance and equipment purchase, such as road construction and re-gravelling and 20% is for routine maintenance.
Maintenance work includes carriageway grading, re-gravelling of certain sections and the installation of road signage. There are plans to install about 30 signs in various areas, including give-way, stop, and speed hump signs.
“We are working on the construction of Guzha Road in Ward 1, an area popularly known as Chikwanha. In 2024 and 2025, we constructed a total of 2 km; 1,3 km in 2024 and 0,7km in 2025. Our goal is to complete the entire stretch, and approximately 1,3km remains outstanding,” said Engineer George.
He said that from 2023 to 2025, the local authority received 100% of its disbursements under the Emergency Roads Rehabilitation Programme (ERRP), though budgeted allocation was reduced to about 50% last year. With this year’s allocation there is confidence that the remaining 1,3km at Chikwanha will be completed.
Provided that funds are available, the local authority also plans to install traffic lights in the area.
Council also constructed approximately 400 metres of storm water drainage at Chikwanha, although significant sections of the road network still require drainage systems.
The local authority intends to further increase its targets through new road construction. Maintenance efforts will continue to focus on carriageway grading and re-gravelling. Since most roads in the district are gravel, the council will also carry out spot gravelling and pothole patching.
Manyame RDC manages to maintain 100% of its roads in 2025