MORRIS BISHI
BIKITA – Bikita Rural District Council (RDC) has accelerated its road rehabilitation programme with 71,3km attended to within just one month.
Acting District Engineer, Victor Chikomo told Masvingo Mirror that the distance was covered from June to July and the aim of the rehabilitation programme is to improve access to schools, villages, clinics and business centres across the district.
The works include motorised road grading, bush clearing, culvert cleaning, shoulder regravelling and pothole patching on key roads in several wards.
Engineer Chikomo said road maintenance remains one of council’s priorities as it seeks to improve mobility and support socio-economic development.
“Between last month and this month, we have completed 71,3km of routine road maintenance. The works include road grading, bush clearing and culvert cleaning on roads across the district,” said Chikomo.
Council rehabilitated 4.5km Nyemba School access road, 2,1km Munhande Village access road, 2km Kurumauone Dam access road, 1,5km Chirumba School access road and the 3,5km Mutsenha Village access road all in Ward 9.
Road works were also carried out on the Silveira – Bikita Road in Ward 15 which links Wards 28 and 9. The 0,7km Murambwi Village access road was also rehabilitated.
The district’s biggest project is the 24km motorised grading of the Silveira – Beta Road connecting wards 28, 15 and 16.
“We have also graded seven kilometres of the Museti-Mudzani Road, with the remaining section to be completed,” he said.
At Nyika Commercial Centre, council is carrying out shoulder regravelling on a nine-kilometre surfaced road and similar works and pothole patching are underway in Duma Residential Area.
Chikomo said work is continuing on the strategic Nandi-Matsvange Road, which links Makuvaza, Matsvange and Mashoko.
“This is one of the major roads in the district and road grading is currently underway,” he said.
To improve road safety, Bikita RDC has installed speed humps along the Masvingo-Mutare Highway near Gwindingwi and Gumunyu schools.
Chikomo said traffic lights have also been installed on the highway, with another set planned at the busy intersection to Zaka near Matimba Garage.
“We are not only improving the road network but also enhancing road safety for motorists, school children and pedestrians using some of the district’s busiest roads,” he said.